Marjorie Street Pumping Station
A Public Preconstruction Meeting was held on April 23, 2024, on-site at the pumping station at the end of Marjorie Street.
This project involves building a small new wastewater pumping station, which will provide services within the Marjorie Street and Sylvester Street area.
For presentation to the Planning Board on July 15, 2021, click here.
Start: Tentative start date, September 3, 2024
Substantial completion: December 31, 2024
Final completion: January 31, 2025
Estimated construction cost: $1,776,335
Design Engineer: Wright Pierce
Contractor: Albanese D&S, Inc.
This project involves building a small new wastewater pumping station, which will provide services within the Marjorie Street and Sylvester Street area.
For presentation to the Planning Board on July 15, 2021, click here.
Project Manager:
Christine Sproviero, Project Manager
Office: (603) 766-1755
Email: crSproviero@cityofportsmouth.com